Information for neighbors

Construction updates

For the Block Association’s latest reports from the project team, read the dated construction newsletters below. To ask about current work or raise a neighborhood concern, contact the Block Association.

Past closure notices are preserved in the project history below and should not be read as a current street-closure schedule.

Project history · 2023–2026

2023

Following the first filed plans

In November 2023, the Block Association shared reports of development plans filed for 38 Gramercy Park and an adjoining Third Avenue site. The Block Association told neighbors it was following the proposals and would continue to advocate on their behalf.

That early notice begins the sequence of updates below. Later construction, tree-removal and replacement discussions developed from proposals that were still being monitored in 2023.

2024–early 2025

Understanding the proposal

A March 2024 letter introduced the development assembling 37 and 38 Gramercy Park East with properties on Third Avenue. The Block Association returned to the project in March 2025 after meeting the developer, Legion, to discuss limiting disruption and protecting the surrounding neighborhood.

Spring 2025

Demolition and the condition of the block

An April update relayed the developer’s plans for demolition on Third Avenue, including flaggers and dust-control measures. By June 17, the developer reported that the Third Avenue demolition was complete, while work at the Gramercy Park buildings continued.

In a separate June 3 letter, the Block Association raised litter, graffiti, tree-garden conditions and standing water near the crossing. The developer described a planned response.

July 2025

Street trees and a future replacement commitment

A July 1 letter explained that Parks had approved removal or relocation of five East 21st Street trees affected by construction. It also described protection for other nearby trees.

The developer’s stated replacement plan looked ahead to fall 2027 and trees of the largest size the City would permit.

A July 10 follow-up reported that the Block Association had raised neighbors’ objections and asked the developer to explore keeping the trees. The developer said it had found retention infeasible and scheduled Bartlett for the removal work. Replacement locations and numbers were still being developed around underground utilities and other constraints.

August 2025

Hours, access and the next stages

Late-August letters described demolition access from Third Avenue, debris removal and the changing scaffolding. The Block Association also reported negotiating a later weekend start, around 10 a.m., in response to neighborhood concerns.

The project team supplied a schedule extending into 2028. Later letters record how the work progressed.

November 2025

Protecting the streetscape during demolition

A November 13, 2025 update relayed the developer’s report that demolition at 37 Gramercy Park East and 38 Gramercy Park was complete. It also described planned removal of a remaining street tree and the developer’s replanting commitment.

Neighbors had raised the historic bishop’s-crook lamppost on East 21st Street as a particular concern. The Block Association reported that the developer had engaged a DOT-recommended vendor to remove and store the fixture to protect it from construction traffic, with restoration if needed and reinstallation after the project.

December 2025–January 2026

Making the crossing more visible

A December 15 letter reported installation of a convex mirror and warning signs at the difficult corner of East 21st Street and Gramercy Park East. Neighbors continued to identify blind spots, prompting another conversation with the developer.

January 2026

Acting on a difficult crossing

Neighbors continued to report blind spots at East 21st Street and Gramercy Park East. The Block Association took the concerns back to Legion, including questions about the construction shed and the angle of the safety mirror.

The January 13 follow-up reported a readjusted convex mirror, an additional barrier directing pedestrians toward the existing crosswalk, supplemental signs and removal of a jobsite viewing window that had encouraged people to gather at the corner. The developer had worked with DOT on the changes, according to the letter.

April 2026

Questions go back to the developer

Following an April project update, residents asked about working hours, noise and environmental remediation. The Block Association put the questions to Legion and circulated the responses on April 23.

The developer described its review of site activity and the progress of soil removal and groundwater and vapor-management systems.

August 2026

The structure rises

On August 6 the Block Association relayed the developer’s report that concrete placement had reached part of the sixth floor and that the temporary construction hoist was operational. The update also described work at street level and the Block Association’s attention to sanitation and rodent concerns.

When a later concrete operation continued into the night, neighbors reported the disruption. The Block Association contacted senior management, shared the explanation and asked for confirmation of after-hours permit coverage. Read the August 13 response.

September 2026 · Archived notices

Helping neighbors plan

The project team’s September 16 notice announced planned closures of East 21st Street, from Third Avenue to Gramercy Park, for water-main connections on September 19–20 and 26–27, 2026, from 8 AM to 6 PM each day. These dates have passed; the notice is retained here as part of the project history, not as a current closure schedule. Read the original September 16 notice.

Following concerns about late-night work, the project team told the Block Association it would give advance notice, or notice as soon as possible, of disruptive after-hours work.

October 2026

Advance notice and water service

After neighbors reported late concrete pours, the developer said it would try to provide advance notice of particularly disruptive work or extended hours when practical. The bulk of heavy concrete operations was estimated to continue toward the end of November, subject to conditions.

The same update addressed recurring leaks near the hydrant used by the site. The developer said the project expected to switch to permanent water service in the coming weeks and attributed the leak to DEP piping; no repair date had been provided. Read the October 12 update.

What stays constant

Construction changes from month to month. The Block Association’s role is to keep a line open: gather residents’ concerns, take them to the project team and public agencies, and report back.

Reinforcing steel and a concrete-pump hose on an upper floor of the construction site.
Construction at 38 Gramercy Park, pictured in the August 2026 update.
A pedestrian barrier at the construction-site corner.
The additional barrier pictured in the Block Association’s January 2026 safety follow-up.
A convex traffic mirror below Gramercy Park street signs.
The traffic mirror discussed in the same follow-up.
Sources

Adapted from the Block Association newsletters from March 2024 through October 2026, including its April 24, June 3, June 17, July 1, August 27 and August 30, 2025 project updates.